| Current Projects | White Drive Sanitary Sewer | BNSF Waterline Relocations |
| Center & Main Street Intersection Improvements | 159th Street Guardrail Upgrade | 167th Street Realignment |
| Grand Street Improvement |
The Center Street and Main Street Intersection project will provide additional turn lanes and signal modifications at this intersection in the heart of Gardner. The project’s primary purpose is to improve safety and relieve congestion. Dedicated left-turn lanes will be added on both approaches to the intersection on Main Street. Traffic will be maintained throughout construction as well as access to all adjacent properties.
Construction of this project is funded by the Kansas Department of Transportation. The City of Gardner is responsible for funding the engineering design, right-of-way acquisition, utility relocation, and construction observation.
Construction is scheduled to begin in the spring of 2013 and should be completed by the fall of 2013.
For more information, please contact City Engineer Tim McEldowney (tmceldowney @gardnerkansas.gov) at 913-856-0959; or Project Engineer Mark Pottinger (mpottinger @gardnerkansas.gov) at 913-856-0918.
City staff will prepare construction plans to remove the curves and straighten W. 167th Street, just west of Waverly Road. This work should begin in 2013.
This project is located on W. 159th Street, 1000' east of Kill Creek Road. The City is currently designing replacement guardrails for the box culvert at Kill Creek. This project will be approximately 500' long, consisting primarily of guardrails, grading, and seeding. Construction is expected to begin in October of 2012. The street will be closed to through traffic from Monday, November 12, through Friday, November 30. The primary detour route will be 167th Street, detour signs will be posted.
The Gardner City Council approved Resolution No. 1865 on March 5, 2012, accepting the Benefit District Petition submitted by USD #231, and creating and authorizing debt financing for a benefit district to construct Grand Street, water line improvements, and sanitary sewer improvements. Grand Street will be constructed as a collector roadway from its current termination east of Center Street to Cedar Street. The project will include pedestrian and bicycle facilities and geometric improvements at the existing intersections of Grand Street with both Center Street and Moonlight Road. The work will also include a traffic signal at the intersection with Moonlight Road. It is anticipated that work will commence in mid-December and be substantially complete by June 1, 2013. All work on this roadway will be completed and the road will be open to the public by the beginning of July, 2013.
Design of this project was completed in May of 2012. Right-of-way and easements are currently being acquired, with all easements having been accepted except one. Construction is expected to begin in mid-December, 2012.
This project consisted of one waterline relocation at Sycamore and Warren Streets, and one north of 183rd Street and Waverly Road. Abandoned lines at Center Street, Sycamore Street, Waverly Raod, and between Waverly Road and Center Street were removed. Work is expected to be completed by mid-November, 2012.





















